The project entity shall submit the fixed asset investment filing form and the distributed PV power generation project filing application form to the municipal or county-level energy authority. The application should include the following materials:
1) A project plan that complies with the regulations on installing PV power generation systems on buildings and other facilities;
2) Proof of use of the project site, such as land or roof;
3) A grid connection access opinion issued by the municipal or county-level grid company;
4) If the project adopts an energy management contracting (EMC) model, an energy service management contract signed with the electricity user and other relevant materials;
5) Other materials required by local government in accordance with relevant regulations.