Dealer Handover Inspection: Unboxing, Open-Circuit Voltage and Test Ride Records

2026-11-28 09:35 CHISEN Technical Team

Three weeks after a container of 6-DZF-20 blocks was signed for, a dealer found four blocks that would not hold charge. The supplier asked three questions: what was the open-circuit voltage on arrival, what was the pack voltage at handover, and which charger ran the first cycle. There was no answer on file, so the four blocks were treated as unproven. The blocks may have been fine. The paper trail was not.

This article sets out a dealer-side process with three gates — unboxing, open-circuit voltage (OCV) and a recorded test ride — plus the numbers to write down at each gate. It is written for workshops and distributors receiving 12 V lead-acid blocks for e-bikes, e-scooters and light electric vehicles; the same structure works for the 6-DMF and EVF series.

Gate 1: Unboxing inspection, before the pallet leaves the loading bay

Work from the packing list, not from memory. Open at least one carton per pallet, and every carton if the shipment moved by sea with transhipment.

  • Count and model match. Carton count against the packing list, then the model code on every block against the order. 6-DZF-12 and 6-DZF-20 look alike on a wrapped pallet; the 12 Ah block is 99 mm tall and the 20 Ah block is 170 mm, so a mixed pallet shows up as soon as you use a tape measure instead of the label.
  • Weight per block. A 20 kg shortfall on a pallet is a missing block; a 300 g difference on one block is a grade mismatch. 6-DZF-20 ships in six weight grades spanning 6.10–7.00 kg, and the grade is fixed by the purchase order — weigh against the grade printed on that order, not against the nominal model.
  • Terminals. 6-DZF-12 uses Φ8.0-M5 posts, 6-DZF-20 uses Φ8.8-M5. A post that does not match the harness is a shipping error, not something to fix in the workshop.
  • Physical condition. Case swelling, electrolyte weeping at the bushings, cracked lids and a legible date code. Photograph any defect with the carton label in the same frame.

Write the date, container number, carton count and every exception on one sheet and keep it for at least the warranty period. This sheet is the first document an OEM will ask for.

Gate 2: Open-circuit voltage, read after rest and corrected to 25 °C

OCV tells you state of charge, not capacity, and it only means something after the block has rested. A block measured straight off a truck that spent two days at 45 °C reads high; one measured in an unheated warehouse at 0 °C reads low. Let the blocks rest 4–8 hours at room temperature for the first reading, then re-read any block that fails.

OCV per 12 V block at 25 °C, rested 4–8 hInterpretationDealer action
at or above 12.70 VFull or close to itRelease to stock
12.40–12.69 VNormal for a block that has been storedRelease, log the value
12.10–12.39 VRoughly half to three-quarters chargedTop up before first delivery; do not store further at this level
11.90–12.09 VDeeply discharged for a new blockQuarantine, one full charge at 0.28I2, re-read after rest
below 11.90 VSulphated or internally shortedDo not release; photograph and open the claim the same week

Two practical notes. First, correct the reading: a rested block drops roughly 0.02–0.03 V per 12 V for every 10 °C below 25 °C, so 12.70 V measured at 5 °C corresponds to about 12.75 V at 25 °C. Second, use a meter that resolves 0.01 V and touch the post itself, not the clamp — a 0.15 V drop across a corroded clamp is the most common false alarm in an intake inspection.

Gate 3: First charge and a recorded test ride

Charge before delivery, then ride. A 12 V block takes a finish voltage of 14.7–14.9 V, with 14.8 V recommended, at 0.25–0.30I2 with 0.28I2 recommended, and temperature compensation of −3.0 mV/°C. Put the charger model and its measured output on the handover sheet: a large share of “failed in a week” cases ends with a charger set for a different chemistry or a different number of blocks in series.

For the test ride, record pack voltage before the ride, distance, terrain, ambient temperature, load class and pack voltage after the ride. Two numbers matter most: the resting pack voltage ten minutes after the ride, which should recover to at least 12.2 V per 12 V block, and the range against the baseline you set for that model. A single weak block in a four-block series pack shows up here as a pack that sags early even when every block passed the OCV gate, so read per-block voltage after the ride whenever the pack is accessible.

The one-page handover record

FieldWhy it is worth writing down
Block model, weight grade, date codeLinks a later claim to one production batch without guesswork
OCV per block on arrival, rest time, temperatureSeparates transport discharge from a defect
Charger model, output, charge start and endRules out overcharging or undercharging before the supplier is asked to pay
Test ride distance, load, ambient temperatureTurns a range complaint into a figure you can compare with a baseline
Photos: label, terminals, carton, meter displayA photograph of a 12.01 V reading is worth more than the figure typed into an email

The 6-DZF and 6-DMF blocks we supply are produced and tested to GB/T 22199.1-2025 and T/ZJXDC 001-2021, and the EVF series to GB/T 32620.1-2016 and GB/T 32620.2-2016. Those are the standards named on the accompanying documents. Your own acceptance thresholds remain a commercial decision and can be tighter — the OCV table above is a starting point, not a replacement for your warranty terms.

What this changes for a distributor

A dealer who runs these three gates settles most routine complaints inside the workshop. A low-OCV block is charged and re-read before anyone files a claim, a charger mismatch is caught at handover, and a genuine defect reaches the supplier with a photograph, a reading and a date attached. That is the difference between a claim and an argument.

ZHEJIANG CHISEN BATTERY CO.,LTD manufactures 6-DZF, 6-DMF and EVF lead-acid blocks for e-bikes, e-scooters, wheelchairs, golf carts and light electric vehicles, and works with OEM and wholesale buyers on custom labelling, nameplates in the buyer’s language and the export documentation the destination market requires. If you are setting up a receiving process for a new range, send us the model list and the destination port and we will confirm the weight grade, terminal type and the documents we can issue for that order.